2016 3月
The Kings Domain Apartments are progressing smoothly with basement works now underway. Preperation for piling works have commenced with guide walls being installed. It is estimated that construction will be complete by November 2017. 公寓进展非常顺利,地基工作正在做,打桩和导墙安装已准备就绪。 项目预计2017年11月可完工。
|
|
|
|